Australia approved a record $21.5 billion of data centre building in a year, and Victoria is finishing the work nearly 5 times faster than New South Wales

Data centre approvals hit an all-time high in the year to September, but the states are splitting on delivery: Victoria is completing projects at pace while New South Wales approves more and builds slower.

WorkClone Research

Key findings

  • Australia approved $21.5 billion of data centre building in the 12 months to September, a record and 2.5 times the year before
  • Victoria’s September approval of a $2.2 billion project is the second-largest of its kind on record, behind only a $3.1 billion Sydney project in May
  • New South Wales approved $10.2 billion over the 12 months to September, while Victoria approved $9.0 billion
  • Victoria completed work worth $1.5 billion in 2025-26, 61 per cent of the national total
  • Victoria completed data centre work at nearly 5 times the rate of New South Wales in 2025-26
  • Victoria had $9.7 billion of projects under construction at June, with $3.5 billion already built and $6.3 billion still to come
  • At Victoria’s completion rate, an estimated 1.9 years of work remains on projects already under way, compared with 4.7 years in New South Wales
  • Across Australia, $18.9 billion of work was still to be done on projects under way at June, the most since records began in 2001
  • Two-thirds of unfinished work, $12.6 billion, is outside Victoria, with $10.8 billion in New South Wales
  • Data centre building accounted for 29 per cent of all private non-residential building approved across Australia in the 12 months to September

What it means

Victoria is completing data centre projects at a significantly faster rate than New South Wales despite approving fewer projects nationally. “Victoria is where the infrastructure build of the AI boom is being built,” said Natalie Ashes, CEO of WorkClone.

The majority of Australia’s unfinished data centre work remains outside Victoria, concentrated in New South Wales, where projects are being approved faster than they are being delivered.

Methodology

Based on Australian Bureau of Statistics building approvals and building activity data for the data centre category, covering the 12 months to September 2026 and the 2025-26 financial year. Records begin in 2001.